Mount Juliet's Road Projects Reach Your Closing Long Before the Bulldozers Do

"Any authorized changes in roads, drainage or utilities affecting the property, or contiguous to the property?"

That question appears on Tennessee's Residential Property Condition Disclosure. It sits in the section where a seller checks yes, no, or unknown. It doesn't ask whether a road is under construction. It asks about authorized changes. In Mount Juliet, two major road projects are moving through approvals and right-of-way funding right now, and construction on either one is still years away.

For anyone buying or selling near Central Pike or Lebanon Road, the timeline matters more than the finished road. Building the road is the short part. The long stretch before it is engineering, appraisals, acquisition notices, and easements. That paperwork reaches property owners first, and it lands in the middle of home sales happening today.

Eighteen Months of Construction, Six Years of Everything Else

In August 2026, Mt. Juliet announced a $12 million federal grant to widen Lebanon Road to five lanes between Park Glen Drive and Curd Road. The Tennessean describes the segment as a congested 1.2-mile stretch where traffic "often becomes a crawl." It also reports that the federal money is for right-of-way acquisition.

The schedule shows how the work splits up. NewsChannel 5 reported the city's share at about $3 million for this phase, with the full project expected to take about 6 to 8 years. Most of that time goes to engineering and acquisition. Construction itself is estimated at 12 to 18 months. On a seven-year project, crews would be working for about a year and a half. The rest of the schedule is surveys, appraisals, and negotiations with property owners.

Earlier steps are already underway. On Aug. 4, 2026, the city published an engineering request for qualifications. It covers widening Lebanon Road from two lanes to five, with traffic signals, bike lanes, and sidewalks, and responses were due Aug. 28. The project limits aren't settled. The RFQ describes the area from near Park Glen Drive to Terrace Hill Road, while news coverage uses Park Glen to Curd. A 2025 Chronicle of Mt. Juliet story put the Lebanon Road project at 2.7 miles. Anyone with a contract on a property near the corridor should treat the final boundary as an open question.

New homes also keep coming while the road stays the same. City Commissioner Art Giles pointed to growth on Benders Ferry Road as a source of Lebanon Road congestion. "It filters out onto Lebanon Road," he told NewsChannel 5. In that same area, John Wieland Homes held a Sept. 12 grand opening for Treymor at 122 Treymor Drive. The community covers 317 acres, with 349 planned homes, 166 acres of open space, and prices starting at $649,990. The Tennessean reported that home construction there was set to start in October. Those homes will probably be built and occupied years before Lebanon Road gets its extra lanes. A buyer should judge a commute by the road as it exists today, because the planned version is a long way off.

Central Pike Is About to Enter Its Right-of-Way Phase

Central Pike is further along, and its next public step is coming soon. The two projects side by side:

I-40 / Central Pike Interchange Central Pike Widening Lebanon Road Widening
Scope New diverging diamond interchange Five lanes from I-40 to Mt. Juliet Road Five lanes, Park Glen Dr. to Curd Rd. area
Key funding $24.6M federal grant, construction must start by 2029 City-managed engineering, TDOT right-of-way and construction $12M federal grant for right-of-way, about $3M city share
Next milestone TDOT right-of-way meeting expected Q4 2026 / Q1 2027 Follows the interchange Engineering selection after August 2026 RFQ
Construction estimate Start in FY2029 Start in FY2030 12 to 18 months, inside a 6 to 8 year total timeline

On Sept. 14, 2026, the Mt. Juliet Board of Commissioners voted unanimously to approve TDOT's proposal setting out the city's obligations for the interchange. Those obligations include:

  • closing or modifying some roads
  • transferring city-owned land to TDOT at no cost for right-of-way or easements
  • removing or adjusting city utilities
  • maintaining any frontage road that gets built
  • making no changes to road segments inside the acquired right-of-way

The same Chronicle of Mt. Juliet article ties a $12 million grant to the interchange. Other local coverage identifies that $12 million as the Lebanon Road right-of-way award. The interchange's federal grant is $24.6 million, and it requires construction to start by 2029.

TDOT's project page says preliminary engineering on the interchange is underway. It lists completion as "TBD." The planned design is a diverging diamond, chosen to handle heavy left-turn volumes from Central Pike. In the interchange area, Central Pike goes from two travel lanes to four, plus turn lanes, signals, and sidewalks.

The schedule has already changed once. In August 2025, the city voted to ask TDOT to move the interchange up from 2031 to 2029 and to push the Central Pike widening from 2030 to 2032. TDOT's live page still shows the widening in FY2030. Anyone using a construction year to plan a purchase should treat it as an estimate.

What the Right-of-Way Phase Sends to Property Owners

TDOT's process runs in a set order. Knowing that order tells an owner how far along a project really is.

  1. Right-of-way public meeting. TDOT holds this at the end of design to show the final proposed right-of-way plans. It's a chance to review the plans. Nobody receives an offer at this meeting.
  2. Notice of Proposed Acquisition. Once the plans are released for acquisition, affected owners get this notice. Title work, appraisal, and appraisal review follow.
  3. Appraisal. An appraiser inspects the property and values it at fair market value using public records and recent sales. If TDOT is taking only part of a lot, the appraisal also covers how the taking affects the land the owner keeps.
  4. Written offer. A TDOT agent explains how the project affects the property and presents an approved offer. The owner can negotiate, and TDOT says an item of value or damage that was missed can lead to an adjusted appraisal.
  5. Condemnation if there's no agreement. TDOT deposits its offer amount with the court. The owner can withdraw that deposit while the final award is still being decided.

For Central Pike, step one is the meeting TDOT expects in Q4 2026 or Q1 2027. That's the next few months. For homes near the interchange, the first public look at final right-of-way plans could come before a contract signed this fall closes.

In practice, most takings are partial, and TDOT's preliminary interchange materials from the Feb. 29, 2024 design meeting show what that looks like. A listed tract shows 1,937 square feet to be acquired and 0.986 acre remaining. It also carries a 2,625-square-foot slope easement and a 1,729-square-foot construction easement. That table comes from a preliminary design, so it doesn't predict which parcels the final plans will touch. It does show the usual pattern of a small piece of frontage plus easements, with the rest of the lot staying with the owner.

The easements stay with the land. According to TDOT's FAQ, slope and permanent drainage easements leave the land with the owner but restrict how it can be used. A construction easement is temporary, and the FAQ describes its term as three or more years from the start of construction. That FAQ is an older document, so the term written into the actual easement is the one that applies.

If a full or partial taking displaces an occupant, relocation help may apply. That can include moving costs and, for qualifying owners or tenants, replacement-housing payments. TDOT's July 2026 brochure says displaced occupants get at least 90 days to relocate after the state takes possession.

Where This Lands on the Disclosure Form

This brings the process back to the seller's paperwork. The Tennessee disclosure form doesn't have a question that names condemnation, eminent domain, or road widening. The two closest questions are the "authorized changes in roads" question and one asking about "any encroachments, easements, or similar items that may affect your ownership interest in the property."

Both questions tie to the right-of-way phase. A city vote, a funded acquisition grant, a right-of-way meeting, and a Notice of Proposed Acquisition each give a seller more specific information than the step before. A recorded slope or construction easement is the kind of item the second question covers. The form asks sellers to answer in good faith to the best of their knowledge. It also tells buyers that the disclosure doesn't replace an inspection and that they must ask about material defects a careful look would reveal. The form gets revised from time to time, so check the current version at the time of the transaction. Exactly what has to be disclosed, and when, is a question for a real estate attorney.

On these corridors, a buyer has a clear list of items to check before the inspection period ends. Compare the parcel to the most recent TDOT or city plans. Ask the seller whether any TDOT notice has arrived. Read the survey date the seller lists on the form against any easement that has come up since.

Quick Answers

Is my property on Central Pike or Lebanon Road being acquired? No public source we found lists affected parcels on either corridor yet. The Lebanon Road project is in the funding and engineering stage. The only Central Pike parcel table we found comes from the preliminary 2024 interchange design. The final right-of-way plans and a TDOT notice will answer it for a specific property.

Does a right-of-way meeting mean an offer is coming? The meeting is where TDOT shows its proposed plans. Offers come later, after the Notice of Proposed Acquisition, title work, and appraisal.

When will the new lanes actually open? TDOT shows interchange construction starting in FY2029, Central Pike widening in FY2030, and completion as TBD. On Lebanon Road, officials put the whole project at 6 to 8 years, with 12 to 18 months of construction.

If you're pricing a home near Central Pike or Lebanon Road, or thinking about making an offer on one, Move Up Home Group will check where the property sits against the current project timeline before the disclosure gets signed or the inspection period runs out. Let's Get Moving!

This article is general information, not legal, tax or financial advice. Consult a qualified professional about your situation.